Highlands Highway Rehabilitation Program

Date: November 2019

Client: Sustainable Highlands Highway Investments Project (SHHIP) CW1 with association ADB and PEC-Korea

Project type: 210km Four Lane Highway from Nadzab to Henganofi Cadastral & Topographic Survey

About Project

Successfully conducted a Geodetic Control and comprehensive Topographic survey of the 210km stretch of the four-lane Highland’s Highway, spanning from Nadzab Airport to Henganofi Township. This undertaking included the meticulous completion of drawings and the composition of a detailed report, all accomplished within a ten month time frame.

Summary

Conducted topographical surveys for a 35-kilometer road easement and cadastral boundaries exceeding 100 hectares. Executed precise centerline and kilometer pegging for a 36 km road leading to Oil heads and CPF.